Latest construction progress pictures from site at Magdalene College New Library project.

The first floor forest of reinforced masonry columns is taking shape on top of the 375mm thick reinforced concrete transfer slab over the archive and gallery spaces.

The first floor exposed engineered timber elements on the library area have been recently installed and protected along their edges to prevent water ingress until the roof is installed towards the end of this year.

It is exciting to see all exposed structural elements, precast concrete lintels, selection quality engineered timber and handmade brick, coming together for first time.